How to disable Costing of Material Components into Planned total by default?

$
0
0

Hi,

 

We want to disable Material Components planned value addition into the Activity's and Project's Planned total.

 

If we plan a Material for an Activity, the Planned value reflects as follows:

 

Planned Material:

 

 

Activity's Planned Value (CTRL+F11):

 

 

Project Planned Value (as in S_ALR_87013532 and CJ31):

 

 

 

We want that just the Costs Activity's inserted Amount to be taken into consideration:

 

 

Right now, we see we can make this happen if we manually uncheck the "CostRel" (Relevancy to Costing) checkbox on the Material Component:

 

 

 

 

But we want that behavior to be taken by default.

 

Is there any costumizing/SPRO route that we can take to achieve this or something similar?

 

Thanks a lot for the help!!

Leo