Hi,
We want to disable Material Components planned value addition into the Activity's and Project's Planned total.
If we plan a Material for an Activity, the Planned value reflects as follows:
Planned Material:
Activity's Planned Value (CTRL+F11):
Project Planned Value (as in S_ALR_87013532 and CJ31):
We want that just the Costs Activity's inserted Amount to be taken into consideration:
Right now, we see we can make this happen if we manually uncheck the "CostRel" (Relevancy to Costing) checkbox on the Material Component:
But we want that behavior to be taken by default.
Is there any costumizing/SPRO route that we can take to achieve this or something similar?
Thanks a lot for the help!!
Leo