General extra material's requirement when MRP

$
0
0

Hi All,

 

    I meet a problem in our company.  We usually create PIR for our prodcut A,  then run mrp general the PR, PR-->PO, PO GR come to stock, finially SO(product A) PGI to consume the stock and deduct the PIR.  But now we want to general B material requirement at the same time when MRP for product A,  we need to buy A and B at the same time. At last we will 311 transfer B to the special location and consume B by our special program.  My question is :   how to general B requirement at the same time when run MRP for A ?  

    I have 2 methods:  1) create another phantom material C = B+A    ===> This is a little complex, and how to set and deduct PIR ? We don't want to add more new materials;   2) use enhancement/BAdi to create B on the PO when create/change A PO    ===> When first we only have PIR on A, we don't know B  requirement at that time.

    Do you have more better solution?  Thanks!

 

 

BR,

Microfish


Viewing all articles
Browse latest Browse all 3280

Trending Articles



<script src="https://jsc.adskeeper.com/r/s/rssing.com.1596347.js" async> </script>