Hi there,
we actualy set a routing (CA01) with:
0010 Operation A
0020 Quality Control
0030 Operation B
We confirm operations Thru CO11N.
Our goal is to create a dependency so we cant confirm operation 0030 unless we previously confirm Operation 0020 (Knowing that operation 0020 is a quality control).
Is there a way to do so?
Thanks