Hello Expert,
I have raised above points regarding scheduling issue of Order in case MTO, I closed an issue because I wanted to spend sometime in testing before I raise any more, but I'm still struggling to figure out this issue.
I have MTO scenario, in which system creates production order at receipt of sales order. Process order is attached to sales order.
Here I'm talking about two plants.
In plant-1 MTO scenario if sales order has first date (Req. Del. Date) = April/08, then system created process order with backward scheduling options and confirm ATP on same day. This works per business expectation.
While in second plant id sales order First date (Req. Del. Date) = April/13 then somehow system add 1 day and ATP confirm on April/14. If I check order scheduling tab then here system adding 1 day which causing an issue to sales order ATP.
For any day sales order ATP confirm with 1 day delay, I believe which coming from order scheduling tab.
Can you please suggest from where system adding 1 day? I check resource & plant scheduling config but seems same as plant-1.