Order scheduling in MTO scenario

$
0
0

Hello Expert,

 

Scheduling date of PO in MTO

 

I have raised above points regarding scheduling issue of Order in case MTO, I closed an issue because I wanted to spend sometime in testing before I raise any more, but  I'm still struggling to figure out this issue.

 

I have MTO scenario, in which system creates production order at receipt of sales order. Process order is attached to sales order.

 

Here I'm talking about two plants.

 

In plant-1 MTO scenario if sales order has first date (Req. Del. Date) = April/08, then system created process order with backward scheduling options and confirm ATP on same day. This works per business expectation.

 

Plant-2 MTO.jpg

 

While in second plant id sales order First date (Req. Del. Date) = April/13 then somehow system add 1 day and ATP confirm on April/14. If I check order scheduling tab then here system adding 1 day which causing an issue to sales order ATP.

 

For any day sales order ATP confirm with 1 day delay, I believe which coming from order scheduling tab.

 

Can you please suggest from where system adding 1 day?  I check resource & plant scheduling config but seems same as plant-1.

 

Plant-1 MTO.jpg